Woodward


Sabah Electricity (SESB) – Tawau

Telic Engineering was assigned, prior to Covid-19 crisis, to support Mechanical Field Support B.V. and their customer Sabah Electricity (SESB) located in Tawau, Malaysia. Sabah Electricity Sdn. Bhd. (SESB) is an electrical company that generates, transmits and distributes electricity mainly in Sabah and Federal Territory of Labuan, Malaysia. It supplies […]


SASREF Refinery

Telic Engineering was subcontracted to represent Turner Engine Control Solutions (TECS) at SASREF Refinery located in Jubail City, Saudi-Arabia. The task comprised of start-up support and tuning of a Woodward MicroNet TMR steam turbine control system. This task was completed such that SASREF was able to return the steam turbine […]


Jazan Refinery

Telic Engineering received an assignment to represent Woodward Inc. to support their customer Honeywell for closing outstanding Site Acceptance Test (SAT) items at the Jazan Refinery project in Saudi Arabia. Woodward supplies the Compressor Control System (CCS) as part of the automated systems that Honeywell supplies. During this period visited […]


Prelude FLNG II

Telic Engineering returned to the Prelude FLNG to represent Woodward Japan for commissioning of 5009FT Steam Turbine controls, ProTech-GII Overspeed Protection Devices, and TM25LP Actuators supplied to Mitsubishi Corporation and installed on board the Shell FLNG Prelude. This assignment was a continuation of the previous visit to support the solo run in which the […]


Alvheim – FPSO II

Telic Engineering received a second assignment from Woodward Netherlands to support their client Baker Hughes, a GE company, to do control panel wire checks for one of the two turbines used for power generation on board the Alvheim FPSO operated by Aker BP located offshore Norway. Similar checks have been […]


Prelude FLNG I

Woodward Japan requested Telic Engineering to represent them for commissioning of 5009FT Steam Turbine controls, ProTech-GII Overspeed Protection Devices, and TM25LP Actuators supplied to Mitsubishi Corporation and installed on board the Shell FLNG Prelude. Specifically the requested task consisted of supporting the solo run in which the steam turbine is […]


Bapco Refinery

Telic Engineering Ltd represented Turner ECS for commissioning and configuration of a Woodward Peak200 Steam Turbine governor controlling the speed for a new installed Elliott-Ebara Steam Turbine Pump located at Bapco Refinery in Bahrain. The Peak200 is: Field Configurable Integrated graphical operator control panel Simple to install, configure & operate […]


Alvheim – FPSO I

Telic Engineering received an assignment from Woodward Netherlands to support their client Baker Hughes, a GE company, with troubleshooting concerning regular communication errors with I/O devices. This impacted the reliability of one of the two turbines used for power generation on board the Alvheim FPSO operated by Aker BP located […]


Britannia Platform

Telic Engineering Ltd received an assignment to represent MTU Power as their control and instrumentation engineer to support the start-up of a GE LM5000 gasturbine-compressor following a 4000 hour preventative maintenance service on board the ConocoPhillips Britannia platform located offshore, UK. The tasks consisted of monitoring the control system for proper sequencing, […]


Millcreek – Control Upgrade

Telic Engineering Ltd was subcontracted and represented our client during an upgrade at Millcreek Power Station located in St. George, Utah, US. Specifically the hardware was upgraded from a NetCon to a MicroNet Plus control system which interfaces with the existing field devices and on-engine hardware that provide core fuel […]